Extra Work After an Israeli Tender Award: What to Check Before Committing

9/17/2026 · 8 min read
Extra Work After an Israeli Tender Award: What to Check Before Committing

A request for additional work after an Israeli tender award does not guarantee additional payment. Before committing, check whether the work is already included in the price, what the change procedure requires and who can approve the addition and its schedule. A decision to suspend performance because of a dispute also requires a review of the contract and circumstances.

The problem often arises during routine performance: a project manager requests another report, an additional site or a revised deliverable, and the supplier wants to maintain a constructive relationship. A quick agreement can create a gap between what the team delivers and what the public body is willing to pay for. Clarify that gap while the documents and correspondence still allow it to be addressed.

Is the work additional or already included in the price?

Compare the new request with the tender documents, specifications, clarification responses, submitted offer and signed agreement. Check any order of precedence between these documents. Calling something an “addition” in an email does not, by itself, determine whether it is a separate service or part of the promised deliverable.

For a lump-sum contract, examine the defined deliverable and what its completion includes. For a contract priced by quantities or hours, check the measurement units, caps and reporting approvals. A supplier’s pricing error is different from a change requested by the customer. Repeating work to remedy a defect should also be distinguished from expanding the original assignment.

One contract-specific illustration appears in the Government Housing Administration’s tender 06/2025 documents: the agreement distinguishes updates included in the work from certain changes affecting payment, and requires signed work orders and updated orders where a change affects the price. This illustrates why the particular contract matters; it is not a uniform rule for all Israeli tenders.

Who can authorize a change in a public contract?

Start with the identity of the person requesting the work. Check whether that person can issue technical instructions, approve performance, change the price or commit the public body to additional expenditure. Do not assume that technical approval of a deliverable also authorizes additional payment.

Locate the change procedure, signature requirements and approvals in the agreement and procurement documents. Ask who has the necessary authority and which document records the approval. A government ministry, municipality, public corporation or other body may operate under a different framework. Where authority is unclear, the rules and procedures applicable to that particular customer must be examined.

If the request substantially changes the scope of the engagement, its implications under Israeli public procurement law also need review. Do not assume that agreement on a price between project personnel is sufficient to authorize every expansion.

What should the price, schedule and change record cover?

Prepare a change record that makes it possible to compare the original commitment with the new request. Its purpose is to establish a common understanding of performance and payment. Preparing it does not replace an approval required by the contract or applicable law.

  • The precise addition: deliverables, quantities, location and exclusions.
  • The pricing basis: an agreed amount, measurement units or hours, associated expenses and VAT where relevant.
  • The effect on milestones, delivery, subcontractor work and dependencies on the customer.
  • Required approvals, the approving person and the relevant order or contract supplement.
  • How performance will be accepted, how the invoice will be submitted and which supporting records will accompany it.

If the addition delays another task, record its effect on the schedule. A revised price does not necessarily revise the delivery date. Check whether insurance or security arrangements are affected, without assuming that every change requires the same adjustments.

How should you respond to an oral or emailed instruction?

A useful response records what was requested, when, by whom and how, in your view, it differs from the agreed documents. Attach an estimate, explain the effect on deliverables and deadlines, and request the necessary approval. Preserve the original instruction as well as your later summary.

Hypothetical example: a supplier engaged to prepare a report for one site is asked for another report covering a different site. Before treating it as additional work, check whether the agreement already covers other sites, how they are priced and who may order them. If a separate expansion is required, address its scope, price and appropriate approval. This example does not describe a client matter.

An email may help establish what was said, but its compliance with the procurement requirements and the sender’s authority still need to be checked. Wording such as “with rights reserved” is not a substitute for resolving authority and price. If an urgent answer is requested and the commitment is unclear, obtain advice before agreeing to perform.

What evidence matters if payment is refused after performance?

Separate the questions: was the work performed, was it accepted, was it properly ordered and was its price approved? A delivery acknowledgement may support the fact of delivery without resolving the other issues. An invoice alone also does not explain why an obligation arose to pay the amount claimed.

  • The original instruction and approvals given before and during performance.
  • Work logs, time or quantity records, interim deliverables and evidence of delivery.
  • The quotation, work order, invoices and correspondence about budget and payment.
  • Reasons for refusal, meeting minutes and document versions showing how the request changed.

Prepare a factual chronology and retain original files. Do not alter a document retrospectively to make it appear that prior approval was obtained. Where formal approval is missing, the possibility of recovering payment requires an individual legal assessment. Neither the conclusion that payment is lost nor that use of the deliverable guarantees recovery should be assumed.

Can performance be suspended because of the dispute?

Do not assume that a payment dispute permits an immediate halt to all services. Review the agreement’s provisions on continuing performance, notices, dispute resolution and remedies, together with applicable law. Distinguish refusing an unapproved new task from stopping existing contractual obligations.

Before suspending work, threatening termination or signing a release, assess the contractual and practical consequences. Depending on the case, options to examine may include a reasoned payment request, escalation to the authorized decision-maker or an interim arrangement. No single route fits every contract, and no fixed notice period should be stated without checking the documents.

Assemble the tender and annexes, clarifications, offer, agreement, orders, change request and correspondence. Add the original and revised schedules, identify completed work, explain what is now requested and flag any approaching decision date. Identify the public customer and the roles of the people who issued instructions or approvals.

If you have not yet signed, the guide to checks before signing after a tender award addresses that stage. Once performance is underway, the focus shifts to documenting changes, approval authority and the connection between the commitment and payment.

Asked to change the work, or refused payment for an addition? Contact Attorney Karin Amsalem for legal advice during public contract performance and a review of the agreement, approvals and correspondence before the next step.

This is general information, not legal advice for a particular matter. Scope, approval authority, entitlement to payment and responses to a dispute depend on the procurement documents, the customer’s identity, applicable law and the facts.

Frequently asked questions

Does all additional work after a tender award warrant extra payment?

Not necessarily. Check whether it is already included in the price, the change procedure and the necessary approvals. Calling it an addition does not establish entitlement.

Is a project manager’s approval enough for additional payment?

Check that person’s authority and the agreement’s requirements. Authority to give technical instructions or accept a deliverable does not necessarily authorize extra expenditure.

Can payment be claimed without a written work order?

A missing written order requires a review of contractual requirements, authority and evidence. Neither an automatic bar to payment nor guaranteed recovery from performance alone should be assumed.

What if the public body refuses payment after the work is done?

Preserve instructions, approvals, pricing, work logs and delivery records, and identify the reason for refusal. Assess the available options under the contract and the circumstances.

Can I stop work until payment is received?

Do not assume an immediate right to suspend. Review obligations, notices and consequences, distinguishing an unapproved new task from work you have already committed to perform.

Related Legal Services

  • Post-Award Tender and Contract Performance Counsel
    Checking contract, performance guarantees, insurance, fines, milestones and risk management after winning.
From Insight to Action

Have an Initial Direction? Now Apply It to Your Case

An article provides a framework. A sound decision requires reviewing the facts, documents and specific risks before moving forward.

Review based on your documents and current stage
Guidance on whether to pause, act or negotiate
Leave your details and we will contact you

Book a Consultation

Leave your details and we will contact you to understand how this topic applies to your matter.

Client Reviews on Google

5.0 / 5 • 27 reviews

View All Google Reviews
michael ashkar★★★★★

It is often said that lawyers are exploitative and unfair people. This office came to erase this stigma. The entire staff there is lovely, and they do their job faithfully. In my case, I dealt with Attorney Hussam Armali, and I must say that I have never met such an honest, decent, and goal-oriented person. Thank you very much from the bottom of my heart 🙏

Dvir Cohen★★★★★

I contacted Karen just to figure out whether it was worth selling a piece of land we inherited or keeping it. She sat down with me and explained the whole picture – rights, taxation, what can be done in the future. She didn’t try to push in a certain direction, and that was the most important thing to me.

Verified Reviewer★★★★★

Karin Amsalem, a professional and thorough attorney of the highest level! Represented us in the process of selling a plot of land that we won in a tender. This is a complex process that includes registering lease rights in the Land Registry, payments to the Land Registry such as consent fees, refunding subsidies for housing and construction, as well as handling the appreciation tax, which includes many expenses. Karin managed the entire process with professionalism, accuracy and attention to detail, while fully protecting our interests as sellers. Throughout the entire process, we felt that we had someone to trust. Highly recommend her!

Recent Articles

View All Articles
Extra Work in Public Contracts | Attorney Karin Amsalem